Overnight Flood Resiliency Installation AT MTA SUBWAY HUNTER'S POINT PORTAL - NYC

The OFC Team coordinated overnight work over a 4-hour window to get a new vertical deploy flood barrier installed from side to side over the NYC Subway tracks. Our team worked through the night to streamline flood device deliveries, off-loading, on-site staging, site preparation, and seamless installation in just 2 hours. This way, the NY train systems were up and running for peak morning commuting – supporting 4 million+ New York commuters and revenue generation.

Overnight Flood Resiliency Installation – NYC

FLOOD DEVICE: FABRIC FLOOD CONTROL BARRIER
SCOPE OF WORK: Design, Supply, Installation
INDUSTRY: Critical Infrastructure

Supporting resiliency and operational continuity, the OFC team followed a fast turnaround to minimize downtime for the NYC Subway System & 4M+ daily commuters. The Orange Flood Control, LLC team is committed to protecting the largest transportation infrastructure in the United States with resilient, custom-designed, and state-of-the-art flood mitigate solutions.  

SITE ACCESS & PREPARATION

The OFC team began site access and preparation to prepare all the necessary tools, equipment, and resources needed for seamless installation. 

FLOOD BARRIER & MATERIAL DELIVERY

Our team coordinates expert material delivery management to ensure coordinated scheduling, on-time readiness, and smooth handoffs. Despite the delayed access to the train tracks, the OFC team prioritizes proactive communication, material delivery, and offloading to meet critical deadlines.

PRE-INSTALL COORDINATION

Pre-installation coordination and planning can directly impact the project’s success – especially for large, heavy flood device installations. After securing access to train tracks, our on-site project managers coordinated with crane operators, site supervisors, and field teams for safe and schedule-aligned execution.

FLOOD BARRIER MOBILIZATION & STAGING

After midnight, the OFC team executed safe, calculated lifting, rigging, and securing flood barrier above the tracks. Our expert on-site logistics directly streamlined safe lifting – navigating narrow timeframes with precision.

FLOOD OPENING PREPARED

Prior to final installation, our team prepared the flood opening, installed rebar, and managed concrete work to improve site accessibility for flood barrier installation.

FLOOD DEVICE INSTALLATION

Our experienced technicians employ industry expertise, onsite coordination, and full compliance with project specifications to set the foundation for flood resiliency initiatives across the country. 

FLOOD GATE ALIGNMENT

At this critical subway station, our solution-driven approach ensures safe, efficient, and aligned installation – without affecting operational efficciency for critical infrastructure.

MINIMAL DOWNTIME & OPERATIONAL EFFICIENCY FOR NYC TRANSIT

Orange Flood Control LLC is proud to maintain operational continuity for the largest public transportation networks in the United States. Our highly coordinated, solution-driven approach maximized operational & transportation services efficiency to support 4 million+ daily commuters.